  • Supply & installation of new air conditioning system as indicated on the drawings of Split duct and FAHU.
  • We will provide the ducts and indoor units for split duct after receiving the advance payment.
  • For the FAHU will need 14 weeks after receiving the advance payment.
  • Ducting. Pre insulated aluminum ducting work will be fabricated as per ASHRAE standards.
  • Outside duct work shall be insulated with 25mm thick 24Kg/Ms fiber glass insulation with 6 Oz canvas cloth & 30-36 Foster/ Fetco.
  • Acoustic lining inside supply air duct for initial 10 ft. with 12mm thick resin bonded fiber glass insulation.
  • Grills/ Diffusers/ Refrigerant-Piping. AIRTRON/BETA/AIRMASTER or equivalent make grilles and diffusers in standard
  • white powder coated finish.
  • Thermostat controls digital supplied with equipment.
  • Refrigerant piping will be (KTC) with Aero flex or equivalent insulation.
  • Vibration isolation pads will be ribbed rubber for units.